President and Finance Minister Anura Kumara Dissanayake agreed to allocate Treasury funds to expand the nation's electricity transmission network. This step will enable renewable energy generated in Mannar, Hambantota and other regions to join the national grid, alongside plans to build four additional transmission lines, Energy Minister Anura Karunathilaka informed Parliament.
Responding to a question from Opposition Parliamentarian Ravi Karunanayake yesterday (21), Minister Karunathilaka stated that inadequate transmission infrastructure, rather than generation capacity, forms the main barrier to integrating more renewable energy into the national power system.
He noted that although renewable energy plants were constructed in the past, the necessary transmission lines to feed that electricity into the main grid were omitted. Work is currently advancing on the transmission system connected to the Sampur power project.
The initial project plan targeted a 300-megawatt capacity, but officials decided to double it to 600 megawatts, with ongoing developments expected to proceed without major delays. Lack of infrastructure previously blocked power generated in Mannar and Hambantota from fully joining the grid.
Discussions with the President secured Treasury funding for the expansion, which remains critical for absorbing renewable power, alongside the planned construction of four new lines.
Responding to a question from Opposition Parliamentarian Ravi Karunanayake yesterday (21), Minister Karunathilaka stated that inadequate transmission infrastructure, rather than generation capacity, forms the main barrier to integrating more renewable energy into the national power system.
He noted that although renewable energy plants were constructed in the past, the necessary transmission lines to feed that electricity into the main grid were omitted. Work is currently advancing on the transmission system connected to the Sampur power project.
The initial project plan targeted a 300-megawatt capacity, but officials decided to double it to 600 megawatts, with ongoing developments expected to proceed without major delays. Lack of infrastructure previously blocked power generated in Mannar and Hambantota from fully joining the grid.
Discussions with the President secured Treasury funding for the expansion, which remains critical for absorbing renewable power, alongside the planned construction of four new lines.
Latest News
Cargills Bank expands partnership with Intellect
Local
23 September 2026
AirAsia, named ‘World’s Best Low-Cost Airline’ again
Local
23 September 2026
Bourse extends rally as profit-taking slows momentum
Local
23 September 2026
Sri Lanka’s farm productivity lags South Asia: IPS
Local
23 September 2026
Hurricane Polo intensifies into rare category 5 storm off the coast of Mexico
Local
23 September 2026
28 Years, millions of listeners: Gold FM celebrates in style
Local
23 September 2026
Union Bank opens third Leasing Hub in Matara
Local
23 September 2026
Russia cuts natural gas output
Local
23 September 2026
Copper could be gearing up for a rally
Local
23 September 2026
Police clarify seat belt rules for children, shorter passengers
Local
23 September 2026