More than 10 billion rupees is currently withheld as penalties and performance-related recoveries from suppliers involved in the substandard coal controversy, and these funds could be utilised to offset losses caused to the State.
Speaking to the media yesterday, Deputy Energy Minister Arkam Ilyas stated that 18 coal shipments have arrived so far, with sixteen shipments provided by the initial supplier and two by the second.
Around 22 million US dollars has already been withheld as penalties, which amounts to nearly six billion rupees. Furthermore, a 15 million dollar performance bond remains in place. Altogether, the withheld amount exceeds 10 billion rupees, which can be used to recover the financial hit.
The issue emerged following the alleged import of substandard coal for the 900 megawatt Norochcholai Lakvijaya Power Plant earlier this year. A report by the Public Utilities Commission noted that the low-quality coal caused operational disruptions, machinery shutdowns, and environmental concerns. The Government, including President Anura Kumara Dissanayake, acknowledged that while the tender process was followed, the supplier failed to meet the required quality standards.
Speaking to the media yesterday, Deputy Energy Minister Arkam Ilyas stated that 18 coal shipments have arrived so far, with sixteen shipments provided by the initial supplier and two by the second.
Around 22 million US dollars has already been withheld as penalties, which amounts to nearly six billion rupees. Furthermore, a 15 million dollar performance bond remains in place. Altogether, the withheld amount exceeds 10 billion rupees, which can be used to recover the financial hit.
The issue emerged following the alleged import of substandard coal for the 900 megawatt Norochcholai Lakvijaya Power Plant earlier this year. A report by the Public Utilities Commission noted that the low-quality coal caused operational disruptions, machinery shutdowns, and environmental concerns. The Government, including President Anura Kumara Dissanayake, acknowledged that while the tender process was followed, the supplier failed to meet the required quality standards.
Latest News
Kushner in the Middle East for meetings with Hamas leader and Egypt's president
Local
16 August 2026
Belgian wildfire doubles in size tearing through nature reserve
Local
16 August 2026
Iranian parliament advances bill to curb foreign influence
Local
16 August 2026
Russia says at least seven killed in largest Ukrainian attack of 2026
Local
16 August 2026
ANC Education celebrates Class of 2026 graduation
Local
16 August 2026
Janashakthi to acquire Continental Insurance for Rs. 5.14 Bn
Local
16 August 2026
Economic analysts warn of ‘vehicle price mafia’
Local
16 August 2026
Assidua Technologies wins dual honours at Global Laurel Excellence Awards
Local
16 August 2026
Global CEO André Lacroix launches Sinhalese edition of ‘Leadership with Soul’
Local
16 August 2026
Trump's Mideast envoys to push for Gaza peace plan
Local
16 August 2026